1956
The first turbo-generator with a capacity of 4 MW and the steam boiler №1 with a productivity of 20 t / h were put into operation.
1961
The turbo-generator №3 with a capacity of 12 MW and the steam boilers № 4, 5 with the productivity of 75 t / h were put into operation, and in 1968 the steam boiler №6 with the productivity of 75 t / h. Fuel - fuel oil. With the start of the №3 turbo-generator, started the development of the centralized heating supply in Balti.
2013
The project thermal Power System of Balti was initiated in partnership with the European Bank for Reconstruction and Development.
2018
Initiation of Phase I of the project "Thermo-energetic system of Balti municipality (S.A. "CET-Nord")". 169 Individual Thermal Points were installed in 120 residential blocks in Balti municipality and the first block was modernized.
2019
A state-of-the-art thermal power plant for cogeneration was put into operation.
2020
Rehabilitation of the domestic hot water system, with several public institutions being reconnected.
2022
Initiation of Phase II of the project "Thermo-energy system of Balti municipality (S.A. "CET-Nord")" and the project for the ratification of the Loan Agreement between the Republic of Moldova and the European Bank for Reconstruction and Development (EBRD) for the implementation of the project "Thermo-energy system of Balti municipality (S.A. "CET-Nord")" was approved.

The form of organization of the enterprise

1957 – 1960
Balti power plant
1960 - 1963
The thermoelectric power plant Balti
1963 – 1963
The thermoelectric power plant Balti, part of the Moldglavenergo enterprises
1992 – 1997
The thermoelectric power plant Balti, part of the state-owned company "Moldenergo"
1997- prezent
Joint Stock Company CET-Nord

The Enterprise's Managers

Iurii Zabuslaev Ivan Corceaghin Boris Rîcov Victor Adamov Valerii Usatîi Alexei Doronin Alexei Doronin Alexei Doronin Alexandr Zazulin Petru Axenti Ion Galagan Marian Brînza

Personalities

Petru Axenti Petru Axenti, former CET-Nord director since January 1999 – April 2012. He was born in 1952 in Calarasi, Republic of Moldova. He graduated from the mechanization faculty of the Chisinau Agricultural Institute (1974). He worked for the mechanization and electrification company in the district of Glodeni. He was the director of state farm Cotovschi in Sadovoe village. Petru Axenti had been appointed as head of CET-Nord in a tough time for the enterprise and it was noted by initiating the process of installing electronic meters for the commercial calculation of electricity and heat on all distribution machines and he initiated the process of upgrading thermal and electrical energy production equipment.


Alexandru Zazulin, has worked since September 1990 – November 2014 as chief engineer at the CET-Nord. He was born in 1948 in Balti. He graduated from the Polytechnic Institute and performed his PhD at the Communication Institute in Odessa. He began his activity in the energy sector in 1969, occupying positions in the Substations Service of the Northern Electricity Networks. In 1990 he was appointed as chief engineer at CET-Nord. Under the leadership of Alexandru Zazulin was successfully accomplished one of the stages of the technical reconstruction of the undertaking which involved Installation and commissioning of the PT-12-35 turbo-aggregate, with a capacity of 12 MW in low vacuum activity, which increased the production capacity and the efficiency of the plant. At the initiative of the chief engineer in 2007 was started the construction of a metrology laboratory to check the heat meters. Between 1998 and 1999, Alexandru Zazulin held the position of interim director of CET-Nord.


Lica Guțu, head of the CET-Nord chemical department from January 1975 to November 2019. He graduated from the chemistry faculty of the State University of Chisinau. Six years after he became head of the department, he initiated the construction of the water-purification plant, which was put into operation in October 1980. In 1988, the sludge compaction station, which is still active today, was put into operation. Lica Guțu has one of the longest-lived and most dedicated department heads of the enterprise, working in this position for more than four decades.